Key technical points of HDPE pipeline construction

HDPE (high-density polyethylene) pipelines have become the preferred pipe material in municipal engineering, water supply and drainage systems, gas transmission and other fields due to their excellent corrosion resistance, flexibility and long life. However, to ensure the long-term stable operation of the pipeline system, standardized construction technology is essential. This article will introduce in detail the key technical points of HDPE pipeline construction, covering the core content of the whole process such as material acceptance, welding process, laying and installation, quality inspection, etc.

 

Preparation work before construction

1. Material acceptance and storage

Pipe inspection:

Check product certificates and test reports (comply with GB/T 13663, ISO 4427 and other standards)

Check the appearance of the pipe: no bubbles, cracks, depressions or impurities, the port is flat and burr-free

Measure wall thickness and diameter deviation (≤±1.5%)

Preparation of pipe fittings and welding machines:

Matching flanges, elbows, tees, etc. must be made of the same material as the pipe (PE100/PE80)

The hot melt welding machine needs to be calibrated for temperature (210±10?) and pressure parameters

Storage requirements:

Avoid direct sunlight, stacking height 1.5 meters, and support with wooden squares at the bottom

2. Site survey and design

Confirm the pipeline direction, elevation, and slope (0.5%) according to the construction drawings

Check underground obstacles (cables, other pipelines) and mark them

Plan welding pits (width pipe diameter + 1m, length 2m)

 

Key points of HDPE pipe connection technology

1. Butt fusion

Applicable scenarios: pipes with DN 90 mm

Construction process:

End milling: use a milling cutter to cut the pipe end to a flat surface with a gap of 0.3 mm

Heating with a heating plate: the temperature is controlled at 200-220°C, and the heating time is adjusted according to the wall thickness (refer to the table below)

Pipe Wall Thickness (mm)

Heating Time (sec)

Changeover Time (sec)

Cooling Time (min)

4-10

30-50

≤5

6-8

10-20

50-80

≤6

8-10

>20

80-120

≤8

10-15

Butt pressurization: pressure is controlled in stages (absorption pressure 0.15MPa, welding pressure 0.2MPa)

Cooling and shaping: It is forbidden to move the pipeline during natural cooling

Key control points:

Even welding flange (height 1/3 of the pipe wall thickness)

No cold weld, carbonization or impurities in the weld

2. Electrofusion

Applicable scenarios: small pipe diameter (DN315mm) or repair work

Operation points:

Scrape off the oxide layer at the pipe mouth (length socket depth of electrofusion sleeve)

Use a barcode scanner to check the electrofusion sleeve parameters (voltage, time)

No water injection or pressurization during cooling

 

Pipeline laying and backfilling specifications

1. Trench excavation and foundation treatment

Trench bottom width: D (pipe diameter) + 0.5m (DN 500mm)

Foundation cushion:

General soil: Lay 10cm sand cushion

Soft soil foundation: Replace 30cm gravel + geogrid reinforcement

Slope control: Use laser level to check, deviation ≤ ± 0.1%

2. Pipeline installation

Pipe lowering method: Flexible sling lifting (wire rope is prohibited from directly contacting the pipe)

Bending radius: 25 times the pipe diameter (avoid stress concentration)

Pier setting: Pour concrete at the valve and tee to fix

3. Backfill technical requirements

Backfilling Layer

Material Requirements

Compaction Requirement

Pipe bottom to 30cm above pipe

Fine sand or gravel ≤10mm in diameter

≥90%

Within 50cm above pipe

Native soil (remove rocks & frozen soil)

≥85%

More than 50cm above pipe

Compacted in layers

≥95%

Notes:

When backfilling, the internal pressure of the pipeline must be maintained at 0.05MPa to prevent deformation

Test the compaction degree layer by layer (ring knife method test)

 

Quality inspection and acceptance standards

1. Non-destructive testing

Appearance inspection: symmetrical weld flanges and no cracks

Ultrasonic testing: spot check the internal fusion of the weld (10% ratio)

Air pressure test:

Strength test: 1.5 times the working pressure, stable pressure for 1h without leakage

Tightness test: 1.15 times the working pressure, 24h pressure drop 1%

2. Common problem handling

Problem Phenomenon

Root Cause Analysis

Solution

Uneven weld bead

Uneven heating plate temperature

Replace heating plate, re-weld

Local pipe depression

Insufficient backfill compaction

Excavate and re-compact

Joint leakage

Incorrect electrofusion parameters

Cut out section, use repair coupler

 

Safety and civilized construction requirements

1. Welding operation area: set up cordons and equip fire-fighting equipment

2. Groove protection: install warning lights at night, and the slope gradient is 1:0.5

3. Environmental protection measures: waste welding shavings are classified and recycled to avoid soil pollution

 

The construction quality of HDPE pipelines is directly related to the life of the system, and the three core links of material selection, welding process, and backfill compaction must be strictly controlled.

Official website: www.phtopindustry.com | www.pefitting.net
Contact us: Email:inquiry@phtopindustry.com | Whatsapp:+86 15093100892
Company address: Room 802, 8th Floor, Building 5, Jinyin Modern City, Jinshui District, Zhengzhou City, Henan Province, China